Overall Assessment
The compaction of the backfill behind the retaining wall has finally passed inspection and work will continue next week. Also, the upper portion of the new parking lot has been cut down to sub-grade and our contractor has agreed to bring in gravel ahead of the curb and gutter for additional church parking.
|
|
|
|
Footings at front wall.
|
Backfill remains at about 50% due to weather delays.
|
|
|
|
|
Basement slab being prepped.
|
Grading new parking lot.
|
|
|
|
|
Additional storm drainage is complete.
|
Grading new parking lot.
|